Question

1 Approved Answer

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected

On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

image text in transcribed

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $140 million instead of $70 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion.

1:

image text in transcribed

2:

image text in transcribed

3:

image text in transcribed

2021 2022 2023 Costs incurred during the year Estimated costs to complete 60 $120 $70 as of December 31 180 70 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. (Enter your answers in millions. Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date = 2021 2022 2023 2021 Recognized in prior years Recognized in 2021 To date Construction revenue Construction expense Gross profit (loss) 2022 Recognized in 2022 To date Recognized in prior years Construction revenue Construction expense Gross profit (loss) 2023 Recognized in prior years To date Recognized in 2023 Construction revenue Construction expense Gross profit (loss) Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Revenue recognized Gross Profit (Loss) recognized Year 2021 million million 2022 million million million 2023 million Suppose the estimated costs to complete at the end of 2022 are $140 million instead of $70 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2022 2022 Recognized in 2022 To date Recognized in prior Years Construction revenue Construction expense Gross profit (loss) 2021 2022 2023 Costs incurred during the year Estimated costs to complete 60 $120 $70 as of December 31 180 70 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. (Enter your answers in millions. Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date = 2021 2022 2023 2021 Recognized in prior years Recognized in 2021 To date Construction revenue Construction expense Gross profit (loss) 2022 Recognized in 2022 To date Recognized in prior years Construction revenue Construction expense Gross profit (loss) 2023 Recognized in prior years To date Recognized in 2023 Construction revenue Construction expense Gross profit (loss) Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Revenue recognized Gross Profit (Loss) recognized Year 2021 million million 2022 million million million 2023 million Suppose the estimated costs to complete at the end of 2022 are $140 million instead of $70 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 using the percentage of completion method. (Enter your answers in millions. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2022 2022 Recognized in 2022 To date Recognized in prior Years Construction revenue Construction expense Gross profit (loss)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing Theory A Systems View

Authors: Hugh Marsh, G A Swanson

1st Edition

089930608X, 978-0899306087

More Books

Students also viewed these Accounting questions