On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $6,720,000. The

On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $6,720,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below.

2014 2015 2016
Contracts costs incurred during the year 2,304,000 1,784,000 1,752,000
Estimated Costs to complete the contract at 12/31 2,816,000 1,752,000 0
Billining to Fabrik during the year 2,560,000 2,800,000 1,360,000

Using the percentage-of-completion method, compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore income taxes.)

2014 2015 2016
Profit/ loss

Using the completed-contract method, compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore incomes taxes.)

2014 2015 2016
Profit/ Loss

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

EDI Security Control And Audit

Authors: Albert J. Marcella Jr, Sally Chan, John Merriam

1st Edition

0890066108, 978-0890066102

More Books

Students also viewed these Accounting questions

Question

Can the human mind be compared to a computer?

Answered: 1 week ago