One of the resources on your project team makes $55000 per year, and works 39.0 hours a week, what is their basic labour rate in
One of the resources on your project team makes $55000 per year, and works 39.0 hours a week, what is their basic labour rate in $/hr. Enter the hourly rate including cents. You can enter more than 2 decimal places to meet the requirement of 5 significant figures