One of your project stakeholder is the director of a business unit. She is also a member of the organization's executive committee. She thinks your
One of your project stakeholder is the director of a business unit. She is also a member of the organization's executive committee. She thinks your project may not yield the necessary returns. Hence, she doesn't attend the project meetings. If you made the PowerInterest Grid of your stakeholders, in which of the following quadrants will you allocate this stakeholder?
A
Low Power, High Interest
B
High Power, Low Interest
C
Low Power, Low Interest
D
High Power, High Interest
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started