Question
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F.
Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks.
Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 30 units of A are required in Week 8, use the low-level-coded bill-of-materials to find the necessary planned-order releases for all components.
Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.
0 Answer is complete but not entirely correct. Period: Item: A OH: I} LT: 2 33: 0 Q: L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item:C'. DH: 10 LT:1 33:0 I3:50 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item: H OH: I} LT:1 33:0 0: L4L Item: D DH: 0 LT:2 33:0 0:50 Item: E DH: 50 LT: t 33: 0 Q: 20!} Item: F DH:15{I LT:1 33:0 Q: L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releasesStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started