Question

1 Approved Answer

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F.

Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks.

Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 52, 52, and 202 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 12, 52, and 152, respectively; all other items have zero beginning inventory. We are scheduled to receive 12 units of A in Week 2, 52 units of E in Week 1, and also 52 units of F in Week 1. There are no other scheduled receipts. If 32 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all components.

Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Period 1 2 3 4 5 6 7 8
Gross requirements
Item A` Scheduled receipts
OH =0 Projected available balance
LT = 2 Net Requirements
SS = 0 Planned order receipts
Q = L4L Planned order releases
Gross requirements

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Book Of Templates

Authors: Navaid Ur Rehman

1st Edition

9798719847344

More Books

Students also viewed these General Management questions