Ottawa Hydro must replace its power pole transformers and has received the following per unit quotes from three transformers manufactures. Which manufacturer should be awarded

Ottawa Hydro must replace its power pole transformers and has received the following per unit quotes from three transformers manufactures. Which manufacturer should be awarded the contract? Note: Ottawa Hydro is a municipal crown corporation and does not pay income taxes

SIEMENS: 9 Cost per unit: $12,500 Operating cost per unit: $3,500 per year Expected life per unit: 8 years

GE: Cost per unit: $11,500 Operating cost per unit: $3,000 per year Expected life per unit: 7 years

MITSUBISHI: Cost per unit: $10,500 Operating cost per unit: $3,200 per year Expected life per unit: 6 years

a)None of these answers

b) GE as its quote has the lowest EAC of $5,134 per unit.

c) MITSUBHII as it is lest expensive.

d) SIEMENS as its units have the longest useful life.

e) SIEMENS as its quote has the highest EAC of $5,593 per unit.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Handbook Of Portfolio Mathematics

Authors: Vince

1st Edition

0471757683, 978-0471757689

More Books

Students also viewed these Finance questions

Question

5. Identify three characteristics of the dialectical approach.

Answered: 1 week ago

Question

7. Identify six intercultural communication dialectics.

Answered: 1 week ago