Question

1 Approved Answer

PATAZAT PARTS LIST LEAD TIME ON HAND Patazat 1 week ( s ) 1 5 Potatozat ( 1 ) 1 week ( s ) 3

PATAZAT PARTS LIST
LEAD TIME
ON HAND
Patazat
1 week(s)
15
Potatozat (1)
1 week(s)
34
1 week(s)
60
Pestarozat (3)
LUGProduct, Ltd. has just received an order for 150 Patazats, which must be ready for delivery at the start of week #8. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand: N.B.: A Patazat is composed of 1 Potatozats). A Potatozat is composed of 3 Pestarozat(s).
When (week #) should an order for Pestarozats be released?
8:06 pm
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions