Question
1 Approved Answer
PATAZAT PARTS LIST LEAD TIME ON HAND Patazat 1 week ( s ) 1 5 Potatozat ( 1 ) 1 week ( s ) 3
PATAZAT PARTS LIST
LEAD TIME
ON HAND
Patazat
weeks
Potatozat
weeks
weeks
Pestarozat
LUGProduct, Ltd has just received an order for Patazats, which must be ready for delivery at the start of week # An MRP planner has prepared the following table showing product structure, lead times orders are lotforlot and quantities on hand: NB: A Patazat is composed of Potatozats A Potatozat is composed of Pestarozats
When week # should an order for Pestarozats be released?