Question
Percentage-of-completion and completed-contract methods.On February 1, 2007, Nance Contractors agreed to construct a building at a contract priceof $6,000,000. Nance estimated total construction costs would
Percentage-of-completion and completed-contract methods.On February 1, 2007, Nance Contractors agreed to construct a building at a contract priceof $6,000,000. Nance estimated total construction costs would be $4,000,000 and the project would be finished in 2009. Information relating to the costs and billings for thiscontract is as follows:
2011 2012 2013
Total costs incurred to date $1,500,000 $2,640,000 $4,600,000
Estimated costs to complete 2,500,000 1,760,000 -0-
Customer billings to date 2,200,000 4,000,000 5,600,000
Collections to date 2,000,000 3,500,000 5,500,000
Percentage of complete gross profit:
2011____________________________
2012____________________________
2013____________________________
Completed-Contract Gross profit:
2011____________________________
2012____________________________
2013____________________________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started