Perfect Perambulators makes upscale baby strollers 3 0 0 days per year. They have a subcontractor supply axles for the strollers with a lead time

Perfect Perambulators makes upscale baby strollers 300 days per year. They have a subcontractor supply axles for the strollers with a lead time of 5 days. The annual demand for axles will be 39,000. The cost of processing an order is $560 per order. The unit cost of the axle is $38.80, and the cost of holding these axles is 12.5% of purchase cost.
Q1. If average demand during lead time is normally distributed with a standard deviation of 25 axles, what is the safety stock quantity if the company wants to maintain a 97% service level? (nearest whole unit)
Q2. If average lead time is normally distributed with a standard deviation of 0.5 days, what is the safety stock quantity if the company wants to maintain a 97% service level? (round to nearest whole)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions