Period 0 Period 1 Period 2 Period 3 Period 4 Period 5 Gross Requirements 100 159 154 173 128 In Transit 10 24 0 0
Period 0 | Period 1 | Period 2 | Period 3 | Period 4 | Period 5 | |
Gross Requirements | 100 | 159 | 154 | 173 | 128 | |
In Transit | 10 | 24 | 0 | 0 | 0 | |
Projected Available | 90 | 55 | ??? | |||
Planned Shipments | 50 | 100 | ||||
MPS (Firm Planned Orders) | 50 | 100 |
The above partial DRP record represents the central warehouse' activity. The safety stock is 15, the lead time is 1 period, and the lot size is 50. The Projected Avaliable is the END OF PERIOD quantity in this record.
Compute the Projected Available quantity at the end of Period 2.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started