Question

1 Approved Answer

PERT network has these time estimates: optimistic = 1.6,most likely =5.4,and pessimistic = 10. What is its expected activity time and variance ? (Do not

PERT network has these time estimates: optimistic =

1.6,most likely =5.4,and pessimistic = 10. What is its expected activity time and

variance?

(Do not round intermediate calculations. Round final answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

How do the building blocks of AON and AOA differ?

Answered: 1 week ago