Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8 - step project. Suppose Pirmin

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash.
Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost ($) Immediate Predecessors
A 210117-
B 315223 A
C 525430 B
D 320124 C
E 630445 C
F 240160 E
G 735650 F
H 1050780 D,G
a. What is the critical path?
b. What is the project length?
c. Which activity should the bike shop crash first , and how much would it add to the project cost?
d. Which activity should be crashed next to reduce an additional hour off the project , and what would be the total cost? (reducing the project by 2 hours)
e. Which activity(s) should be crashed next if you needed to reduce the project by another 2 hours (total 4 hours) and what would be the total cost for the 4 hour reduction

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey

4th Edition

047040292X, 978-0470402924

More Books

Students also viewed these General Management questions