Plasti-Line builds injection-molded plastic signs for fast-food retailers such as McDonalds, Arby's, etc. The company wants to build 80 signs per 8-hour workday using a
Plasti-Line builds injection-molded plastic signs for fast-food retailers such as McDonalds, Arby's, etc. The company wants to build 80 signs per 8-hour workday using a production line. The total task time for each sign is 30 minutes. What is the calculated takt time? Group of answer choices 10 30 16 6