pleaee help write on paper step by step explain to me how to do it You have been assigned as a project manager for a
pleaee help write on paper step by step explain to me how to do it
You have been assigned as a project manager for a new project and are asked to
calculate the budget for it. You have calculated the cost of all work packages as 200,000
USD. The estimated contingency reserve is 40,000 and the management reserve is 6%
of the cost baseline.
Calculate the project budget.