Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

PLEASE ANSWER ALL 5 QUESTIONS. I HAVE EACH QUESTION NUMBERED 1-5. THE LAST CHEGG EXPERT ONLY ANSWERED ONE QUESTION, BUT I REPEAT I NEED ALL

PLEASE ANSWER ALL 5 QUESTIONS. I HAVE EACH QUESTION NUMBERED 1-5. THE LAST CHEGG EXPERT ONLY ANSWERED ONE QUESTION, BUT I REPEAT I NEED ALL 5 QUESTIONS ANSWERED!!! THANKS!

Use the following for the next five questions:

1) The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb..................................................... ..$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.............11,800 Actual price paid for materials........................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct material price variance is.....

A) $600 F

B) $600 U

C) $80 F

D) $80 U

2) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct material quantity variance is:

A) $600 F

B) $600 U

C) $80 F

D) $80 U

3) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct labor rate variance is:

A) $912 U

B) $912 F

C) $2,100 U

D) $2,100 F

4) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct labor effeciency variance is:

A) $912 F

B) $912 U

C) $2,100 U

D) $2,100 F

5) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The total direct labor variance is:

A) $1,188 F

B) $3,012 U

C) $1,188 U

D) Cannot total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Towards A Strategic Human Resource Management Roles Of HR Audit And Org Culture

Authors: Adel Al Samman

1st Edition

3330653051, 978-3330653054

More Books

Students also viewed these Accounting questions

Question

b. Why were these values considered important?

Answered: 1 week ago