please answer all components of the one problem posted The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A B

please answer all components of the one problem posted image text in transcribed
image text in transcribed
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A B C D E F G H B CO DE F G TIMES (DAYS) a 1 4 7 1 3 5 2 5 11 1 8 9 1 2 3 1 6 11 1 2 3 2 3 3 b. What is the critical path? O A-C-F-H OB-E-G-H O A-D-G-H O A-D-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DISTO function to find the correct probability for your computed Z.value. Do not round intermediate calculations, Round "x" value to 2 decimal places and final answer to 4 decimal places.) Probability

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Rigos Primer Series CPA Exam Review Financial Accounting Questions And Answers

Authors: Mr. James J. Rigos

2020 Edition

979-8642293720

More Books

Students also viewed these Accounting questions

Question

List the different categories of international employees. page 642

Answered: 1 week ago

Question

Explain the legal environments impact on labor relations. page 590

Answered: 1 week ago