Question
PLEASE ANSWER FAST AND CORRECLTY QUESTION 1 A CPI or SPI value less than one indicates that the project is a. Under cost or behind
PLEASE ANSWER FAST AND CORRECLTY
QUESTION 1
A CPI or SPI value less than one indicates that the project is
a. | Under cost or behind schedule. | |
b. | Over cost or ahead of schedule. | |
c. | Over cost or behind schedule. | |
d. | Under cost or ahead of schedule. |
1 points
QUESTION 2
Which one of the following is NOT an element of Statement of Work (SOW)
a. | Schedule constraints | |
b. | Performance characteristics | |
c. | Risk analysis | |
d. | Technical requirements |
1 points
QUESTION 3
Using a contractor to perform a high risk task is which form of risk response?
a. | Transfer | |
b. | Acceptance | |
c. | Avoidance | |
d. | Mitigation |
1 points
QUESTION 4
Change control requests:
a. | Are always initiated externally | |
b. | Provide the baseline against which changes will be controlled | |
c. | Are inputs to integrated change control | |
d. | Must be relayed in writing |
1 points
QUESTION 5
Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is:
a. | 16 days | |
b. | 19 days | |
c. | 14 days | |
d. | 20 days |
1 points
QUESTION 6
Which one of the following are conditions preferred for top-down estimation:
- Time and cost accuracy
- Strategic decision making
- Contract price is fixed
- High uncertainty
a. | ii and iv | |
b. | i and iii | |
c. | i and ii | |
d. | ii and iii |
1 points
QUESTION 7
Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?
a. | The same amount of work has been done than planned | |
b. | Less work has been done than planned | |
c. | The project has cost less than planned | |
d. | More work has been done than planned |
1 points
QUESTION 8
The lowest level of the WBS is:
a. | Control account | |
b. | Work packages | |
c. | Code of accounts | |
d. | Deliverable |
1 points
QUESTION 9
An activity has a optimistic duration estimate of 2 days, a mostly likely estimate of 5 days, and a pessimistic estimate of 8 days. What is the PERT weighted average duration?
a. | 4 | |
b. | 5.2 | |
c. | 5 | |
d. | 6 |
1 points
QUESTION 10
Which of the following is NOT true about the Close Project or Phase process?
a. | Stakeholders have least amount of influence at this stage. | |
b. | The probability of completion is the highest at this stage of the project. | |
c. | Contract closeout must be performed after the Administrative Closeout. | |
d. | The risk is the lowest at this stage of the project. |
1 points
QUESTION 11
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called
a. | Task sharing. | |
b. | Outsourcing. | |
c. | Redistribution of projects. | |
d. | Project allocation. |
1 points
QUESTION 12
Which one of the following is a key decision factor for developing relevant quality standards on a project:
a. | design work systems | |
b. | consult project sponsor | |
c. | understand stakeholders' requirements | |
d. | identify cost and schedule constraints |
1 points
QUESTION 13
Using the chart below, what is the cost variance?
a. | $4000 | |
b. | $5000 | |
c. | $3000 | |
d. | $2000 |
1 points
QUESTION 14
Which of the following is NOT part of a modern quality management concept?
a. | Quality must be inspected in | |
b. | Performance standard is zero defects | |
c. | Quality is a 4 cycle process - plan/do/check/act | |
d. | 85% of failures occur because of the process, not the worker |
1 points
QUESTION 15
Which of the following is not part of the quality assurance process?
a. | Operational definitions | |
b. | Quality policy | |
c. | Quality improvement | |
d. | Quality audit |
1 points
QUESTION 16
Which one of the following is NOT a key factor in managing customers' expectations:
a. | Speak the language of the customer | |
b. | Don't oversell the project | |
c. | Avoid sharing project risks information | |
d. | Share signification problems and risks |
1 points
QUESTION 17
Which of the following is an input to the team development process?
a. | Staffing pool description | |
b. | Inputs to performance appraisals | |
c. | External feedback | |
d. | General management skills |
1 points
QUESTION 18
Project teams can often identify risks by conducting any of several types of reviews. Which of the following illustrates a valuable type of risk review?
a. | review the project schedule to determine if certain people are overloaded | |
b. | review previous projects to verify that each current assumption is correct | |
c. | review sunk costs to determine project continuance | |
d. | review the communication plan to determine where poor communications could cause a problem |
1 points
QUESTION 19
A method of shortening the duration of the project is:
a. | Creating milestones | |
b. | Leveling | |
c. | Fast tracking | |
d. | Lead |
1 points
QUESTION 20
An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?
a. | Performance evaluation | |
b. | Scenario analysis | |
c. | Lessons learned | |
d. | Variance analyses |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started