Please answer questions below, no need for explanation. Eight jobs have arrived in the following order: Job Processing Time Due Date 1 8 24 2
Please answer questions below, no need for explanation.
Eight jobs have arrived in the following order:
Job | Processing Time | Due Date |
1 | 8 | 24 |
2 | 4 | 10 |
3 | 10 | 11 |
4 | 3 | 12 |
5 | 9 | 17 |
6 | 6 | 23 |
7 | 15 | 27 |
8 | 5 | 15 |
Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places.
1. Process in the order they have arrived.
Flow Time | Lateness | Tardiness | |
Average |
Shortest processing time
2. What is the SPT sequence 1 through 8?
Flow Time | Lateness | Tardiness | |
Average |
Earliest due date
3. What is the EDD sequence 1 through 8?
Flow Time | Lateness | Tardiness | |
Average |
4. What has the smallest average flow time, Arrival Order, EDD Sequence or SPT Sequence? 5. What has the smallest average lateness, Arrival Order, EDD Sequence or SPT Sequence? 6. What has the smallest average tardiness, Arrival Order, EDD Sequence or SPT Sequence?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started