Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please answer this question showing detailed steps as to how you got the correct answer! Thank you! 1) Use the following for the next five

Please answer this question showing detailed steps as to how you got the correct answer! Thank you!

1) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb..................................................... ..$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.............11,800 Actual price paid for materials........................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct material price variance is.....

A) $600 F

B) $600 U

C) $80 F

D) $80 U

2) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct material quantity variance is:

A) $600 F

B) $600 U

C) $80 F

D) $80 U

Use the following for the next five questions:

3) The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct labor rate variance is:

A) $912 U

B) $912 F

C) $2,100 U

D) $2,100 F

3) Use the following for the next five questions:

The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The direct labor effeciency variance is:

A) $912 F

B) $912 U

C) $2,100 U

D) $2,100 F

Use the following for the next five questions:

4) The following data is given for the Walker Company:

Budgeted production...............................................1,000 units Actual production........................................................980 units

Materials:

Standard price per lb.......................................................$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.........11,800 Actual price paid for materials......................................$23,000

Labor:

Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit.........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928

The total direct labor variance is:

A) $1,188 F

B) $3,012 U

C) $1,188 U

D) Cannot total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Accounting for Governmental and Not-for-Profit Organizations

Authors: Paul A. Copley

10th Edition

007352705X, 978-0073527055

More Books

Students also viewed these Accounting questions