Please anwser the bottom 8 blanks. Show your work please, thanks!
This picture is the answer choice for 3 and 4.
Question 5 (yes or no)
This picture is the answer choise for question 6.
Question 7 (IRR or WACC)
Question 8 (NPV or IRR)
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC 89% 270 390 Project A Project B -1,000 -1,000 650 250 320 255 420 What is Project A'S IRR? Do not round intermediate calculations. Round your answer to two decimal places What is Project B's IRR? Do not round Intermediate calculations. Round your answer to two decimal places If the projects were independent, which project(s) would be accepted according to the IRR method? If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive Sect The reason is Sect Reinvestment at the decision select is the superior assumption, so when mutually exclusive projects are evaluated the approach should be used for the capital budgeting If the projects were independent, which project(s) would be accepted according to the IRR method? 15 Select If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? Luctory -Select- Neither Project A Project B Both projects A and B ct with project acceptance between the NPV and IRR approaches when projects are mutually exclusive? -Select- : The reason Set the NPV and is approaches use the same revestimentos Dumond so both approaches reach the same project acceptance when m y exclusive projects are the NPV and IRR approaches use different reinvestment rate assumption and so there can be conflict in promet ceptance when mutually csive proces are Reinvestmer decision the capital budgeting