Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please draw network diagram and show formulas on excel. ieman Rich Control Devices, Inc, produces custom-built relay devices for auto makers. The most recent project

Please draw network diagram and show formulas on excel. image text in transcribed
ieman Rich Control Devices, Inc, produces custom-built relay devices for auto makers. The most recent project ndertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion me (in days) and those activities that lie along the critical path. The appropriate data are shown in the following fable: a) The expected completion time of the project = days (round your response to (wo decimal places) The activities that represent the project's critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 55 days or less = (round your response to two decimal places) c) The number of days that would result in 99% probability of completion is = days (round your rosponse to two decimal places) ieman Rich Control Devices, Inc, produces custom-built relay devices for auto makers. The most recent project ndertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion me (in days) and those activities that lie along the critical path. The appropriate data are shown in the following fable: a) The expected completion time of the project = days (round your response to (wo decimal places) The activities that represent the project's critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 55 days or less = (round your response to two decimal places) c) The number of days that would result in 99% probability of completion is = days (round your rosponse to two decimal places)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions