Please draw the full diagram and identify the critical path. The project information for the custom order project of the Air Control Company is presented

Please draw the full diagram and identify the critical path.

The project information for the custom order project of the Air Control Company
is presented here. Draw a project network AON diagram for this project
Identify the Critical Path and the legend for your network solution.
ID Description Predecessor Time
A Order Review None 5
B Order standard parts A 8
C Produce standart parts A 3
D Design custom parts B 6
E Software Development B 15
F Manufacture custom hardware C,D 10
G Assemble F 5
H Test E,F,G 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

We spend more time listening than we do talking. True False

Answered: 1 week ago

Question

How did the guard ant recognise this ant ?

Answered: 1 week ago

Question

What did the ants do with the food?

Answered: 1 week ago

Question

Why is cybersecurity critical in smart grid infrastructure?

Answered: 1 week ago