Question

1 Approved Answer

please help me solve for this, please show the working Indiana Co. began a construction project in 2021 with a contract price of $160 million

please help me solve for this, please show the working

Indiana Co. began a construction project in 2021 with a contract price of $160 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million and estimated an additional $53 million in costs to complete the project. Indiana (Do not round your percentage calculated):

Multiple Choice

  • Recognized $3.00 million loss on the project in 2022.

  • Recognized $8.14 million gross profit on the project in 2022.

  • Recognized $8.14 million loss on the project in 2022.

  • Recognized $11.14 million gross profit on the project in 2022.

Prev

Question 17 of 20 Total17 of 20

Visit question mapNext

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Processing Learn About Types Of Audits For Auditors Auditing For Dummies

Authors: Mazie Dannenberg

1st Edition

B097DGKYS7, 979-8524930576

More Books

Students also viewed these Accounting questions

Question

1. Define the nature of interviews

Answered: 1 week ago

Question

2. Outline the different types of interviews

Answered: 1 week ago