please help. urgent. will like Calculate the total overhead variance. The standard cost of product 2525 includes 2.80 hours of direct labour at $13.85 per
please help. urgent. will like
Calculate the total overhead variance. The standard cost of product 2525 includes 2.80 hours of direct labour at $13.85 per hour. The predetermined overhead rate is $21.40 per direct labour hour. During July, the company incurred 5,520 hours of direct labour at an average rate of $14.15 per hour and $110,948 of manufacturing overhead costs. It produced 1,900 unitsStep by Step Solution
There are 3 Steps involved in it