Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

please provide steps / answers to these four questions. I think most of if not all of it has to be done within excel 1

please provide steps/answers to these four questions. I think most of if not all of it has to be done within excel 1. Develop a network diagram (AKA precedence diagram).
2. Calculate the expected duration for each activity. Determine the ES, EF, LS, LF, and slack for each activity.
3. Using your calculations determine the critical path and highlight it on your diagram.
4. Calculate the variance and standard deviation of the project's total duration. What is the probability that the project will be finished within 270 days (that is 270 days or less)? Case Study
Southwestern University Stadium Construction
After six months of study, much political arm wrestling, and
some serious financial analysis, Dr. Martin Starr, president of
Southwestern University, had reached a decision. To the delight
of its students and to the disappointment of its athletic boosters,
SWU would not be relocating to a new football site but would
expand the capacity at its on-campus stadium.
Adding 21,000 seats, including dozens of luxury skyboxes,
would not please everyone. The influential football coach, Billy
Bob Taylor, had long argued the need for a first-class stadium,
one with built-in dormitory rooms for his players and a palatial
office appropriate for the coach of a future NCAA champion
team. But the decision was made, and everyone, including the
coach, would learn to live with it.
The job now was to get construction going immediately af-
ter the current season ended. This would allow exactly 270 days
until the upcoming season opening game. The contractor, Hill
Construction (Bob Hill being an alumnus, of course), signed the
contract. Bob Hill looked at the tasks his engineers had outlined
and looked President Starr in the eye. "I guarantee the team will
be able to take the field on schedule next year," he said with a
sense of confidence. "I sure hope so," replied Starr. "The con-
tract penalty of $10,000 per day for running late is nothing
compared to what Coach Billy Bob Taylor will do to you if our
opening game with Penn State is delayed or cancelled." Hill,
sweating slightly, did not respond. In football-crazy Texas, Hill
Construction's name would be mud if the 270-day target were
missed.
Back in his office, Hill again reviewed the data. (See Table
11.11, and note that optimistic time estimates can be used as
crash times.) He then gathered his foremen. "People, if we're
not 75% sure we'll finish this stadium in less than 270 days, I
want this project crashed! Give me the cost figures for a target
date of 250 days-also for 240 days. I want to be early, not just
on time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sport Management

Authors: Rob Wilson, Mark Piekarz

1st Edition

1138791172, 978-1138791176

More Books

Students also viewed these General Management questions