Please show me how to solve these questions on Excel with formulas, thank you! This table will cover information for Q7-Q8 year CF project A
Please show me how to solve these questions on Excel with formulas, thank you!
This table will cover information for Q7-Q8
year CF project A CF project B
0 -1000 -800
1 600 300
2 700 300
3 300
4 400
With discount rate 7% what is project B's NPV?
QUESTION 8
what is annualized EAC (annualized NPV) for project A?