Please show the process, Thanks! Setup Cost =$651 per setup Holding cost =$0.2 per unit per week Lead Time =1 Week Lot Size = LFL
Please show the process, Thanks!
Setup Cost =$651 per setup Holding cost =$0.2 per unit per week Lead Time =1 Week Lot Size = LFL (Lot-for-Lot) If you have a required safety stock of 140 units, indicate your Net Requirements for Week 2 . 263 margin of error +/0.1Step by Step Solution
There are 3 Steps involved in it
Step: 1