Question
Prepare a direct materials purchasing plan for January, February, and March, based on the following facts. Global GPS Systems assembles its GPS systems with the
Prepare a direct materials purchasing plan for January, February, and March, based on the following facts.
Global GPS Systems assembles its GPS systems with the following costs. Each GPS requires one computer system and four batteries. Computer Systems cost $175 each, and batteries are $2.25 each. Global is able to reliably obtain computers as needed, and does not maintain them in inventory. However, batteries are stocked in inventory sufficient to produce 25% of the following months expected production. Planned production is as follows:
January 22,000
February 41,650
March 21,950
April 22,000
In accordance with the stocking plan, Januarys beginning inventory included 18,000 batteries.
Worksheet 3
Direct materials purchasing plan:
Scheduled production | 22,000 | 41,650 | 21,950 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Raw materials needed: | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Motors (1 per unit) |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Estimated cost per motor |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Total estimated motor cost |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Batteries (4 per unit) |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Plus: Target ending raw material* |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Batteries needed |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Less: Target beginning raw material |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Fan battery purchases |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Estimated cost per battery |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Total estimated motor battery |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Total estimated costs (comput Prepare a direct materials purchasing plan for January, February, and March, based on the following facts. Global GPS Systems assembles its GPS systems with the following costs. Each GPS requires one computer system and four batteries. Computer Systems cost $175 each, and batteries are $2.25 each. Global is able to reliably obtain computers as needed, and does not maintain them in inventory. However, batteries are stocked in inventory sufficient to produce 25% of the following months expected production. Planned production is as follows: January 22,000 February 41,650 March 21,950 April 22,000 In accordance with the stocking plan, Januarys beginning inventory included 18,000 batteries. Worksheet 3 Direct materials purchasing plan:
ers + batteries) |
|
|
|
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started