Prepare a direct materials purchasing plan for January, February, and March, based on the following facts. Global GPS Systems assembles its GPS systems with the

Prepare a direct materials purchasing plan for January, February, and March, based on the following facts.

Global GPS Systems assembles its GPS systems with the following costs. Each GPS requires one computer system and four batteries. Computer Systems cost $175 each, and batteries are $2.25 each. Global is able to reliably obtain computers as needed, and does not maintain them in inventory. However, batteries are stocked in inventory sufficient to produce 25% of the following months expected production. Planned production is as follows:

January 22,000

February 41,650

March 21,950

April 22,000

In accordance with the stocking plan, Januarys beginning inventory included 18,000 batteries.

Worksheet 3

Direct materials purchasing plan:

Scheduled production

22,000

41,650

21,950

Raw materials needed:

Motors (1 per unit)

Estimated cost per motor

Total estimated motor cost

Batteries (4 per unit)

Plus: Target ending raw material*

Batteries needed

Less: Target beginning raw material

Fan battery purchases

Estimated cost per battery

Total estimated motor battery

Total estimated costs (comput

Prepare a direct materials purchasing plan for January, February, and March, based on the following facts.

Global GPS Systems assembles its GPS systems with the following costs. Each GPS requires one computer system and four batteries. Computer Systems cost $175 each, and batteries are $2.25 each. Global is able to reliably obtain computers as needed, and does not maintain them in inventory. However, batteries are stocked in inventory sufficient to produce 25% of the following months expected production. Planned production is as follows:

January 22,000

February 41,650

March 21,950

April 22,000

In accordance with the stocking plan, Januarys beginning inventory included 18,000 batteries.

Worksheet 3

Direct materials purchasing plan:

Scheduled production

22,000

41,650

21,950

Raw materials needed:

Motors (1 per unit)

Estimated cost per motor

Total estimated motor cost

Batteries (4 per unit)

Plus: Target ending raw material*

Batteries needed

Less: Target beginning raw material

Fan battery purchases

Estimated cost per battery

Total estimated motor battery

Total estimated costs (computers + batteries)

ers + batteries)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Make a presentation MKT Milestone on the Perfect 10 Company

Answered: 1 week ago