Question
Prepare a flow process chart for precutting the chords of the roof truss of Figure 20-2 using a single table-mounted power saw. Notice that two
Prepare a flow process chart for precutting the chords of the roof truss of Figure 20-2 using a single table-mounted power saw. Notice that two cuts at different angles (a vertical or plumb cut at one end and an angle cut at the other end) must be made on each chord. Two chords are required per truss. The steps in the process to be charted are as follows: A piece: of raw material is removed from the storage pile, carried to the saw, and positioned on the saw table, one cut is made, and the partially precut piece is removed and placed in a temporary storage pile. After the pieces have all been cut, the saw is reset for the second cut angle, and the process is repeated for the second cut. However, after the second cut the piece is placed into a precut storage pile for use in truss assembly. Use the following job planning data in preparing your flow process chart. The subject to be charted is material.
Hand transport rate, loaded = 2.5 ftls (0.76 m/s) Hand transport rate, unloaded = 4.5 fils (1.37 mls) Job efficiency = 50 minlh Make saw cut = 2 s Position piece at saw == 2 s Power saw to precut storage 25 ft (7.6 m) Power saw to temporary storage = 15 ft (4.6 m) Raw material stack to saw = 15 ft (4.6 m) Remove cut piece from saw = 3 s Remove material from stack = 3 s Stack material = 3 s
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
Step: 1
Based on the provided job planning data including hand transport rates job efficiency saw cut time p...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started