Prepare WIP schedules as of June 30, 2020 Facts: Job A a.Verbally awarded job on December 1, 2019, with a value of $1,000,000 b.Signed contract
Prepare WIP schedules as of June 30, 2020
Facts:
Job A
a.Verbally awarded job on December 1, 2019, with a value of $1,000,000
b.Signed contract on February 2, 2020
c.Men started on the job January 15, 2020
d.As of December 31, 2019, the following costs were incurred
i.Engineering costs of $10,000
ii.Sub-contractor deposit of $10,000 (with a total contract of $60,000)
iii.Total projected costs from the project management team was $800,000
iv.Billings on December 31st were $25,000 before 10% retainage
e.As of June 30, 2020
i.Actual costs incurred $500,000
ii.Pending change orders of $150,000
iii.Billings on June 30th were $800,000 before 10% retainage
Job b
a.Awarded job on October 1, 2019, with a value of $2,000,000
b.Men started on the job December 1, 2019
c.As of December 31, 2019, the following costs were incurred
i.Actual costs incurred $150,000
ii.Total projected costs from the project management team was $1,900,000
iii.Billings were $100,000 before 10% retainage
d.As of June 30, 2020
i.Actual costs incurred $900,000
ii.Pending change orders of $200,000
iii.Projected total costs as of June 30th was $2,260,000
iv.Billings were $1,300,000 before 10% retainage
Job c
a.Job contract value is $1,500,000
b.As of December 31, 2019, the following costs were incurred
i.Actual costs incurred were 1,000,000
ii.Total projected costs from the project management team was $1,100,000
iii.Billings were $1,400,000 before 10% retainage
c.As of June 30, 2020
i.Actual costs incurred $1,130,000
ii.Pending change orders of $50,000
iii.Projected total costs as of June 30th was $1,130,000
iv.Billings were $1,550,000 before 10% retainage
Assignment:
- Prepare WIP schedules as of December 31, 2019
- Prepare WIP schedules as of June 30, 2020
- Prepare June 30th financial journal entries
Key Performance Indicators
Assignment:
Identify your top three KPI's for the following functional areas.Explain the importance and expectations around each KPI.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started