Problem 1 6 - 6 ( Static ) The following table contains information concerning four jobs that are awaiting processing at a work center. Job

Problem 16-6(Static)
The following table contains information concerning four jobs that are awaiting processing at a work center.
Job Job Time (days) Due Date
(days)
A 1420
B 1016
C 715
D 617
Click here for the Excel Data File
a. Sequence the jobs using (1) FCFS,(2) SPT,(3) EDD, and (4) CR. Assume the list is by order of arrival.
b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center. (Round your intermediate calculations and final answers to 2 decimal places.)
c. Which method is superior to the others?
multiple choice
First come, first served
Shortest processing time
Earliest due date
Critical ratio
None are superior

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Book Of Templates

Authors: Navaid Ur Rehman

1st Edition

9798719847344

More Books

Students also viewed these General Management questions

Question

explain the stakeholder theory of the firm

Answered: 1 week ago

Question

Convert from Binary to Octal: 0111112=

Answered: 1 week ago