Question
Problem 1 Find the internal rate of return (IRR) of a project that costs $10,000 and brings net revenue of $8,000 each year for two
Problem 1 Find the internal rate of return (IRR) of a project that costs $10,000 and brings net revenue of $8,000 each year for two consecutive years.
Problem 2 Two projects are proposed to a young start-up company. Project A will cost $250,000 to implement and is expected to have annual net cash flows of $75,000. Project B will cost $150,000 to implement and should generate annual net cash flows of $52,000. The company is very concerned about their cash flow. Using the payback period, which project is better, from a cash flow standpoint? If the discount rate is 10% what is the discounted payback period.
Problem 3 A four-year financial project has net cash flows of $20,000; $25,000; $30,000; and $35,000 in the next four years. It will cost $65,000 to implement the project all of which is needed at the beginning of the project. After the fourth year, the project will have no residual value. Find the net present value of the project assuming 20% discount rate. What is the profitability index of the project?
Problem 4 The annual maintenance on the parking lot is $5000. What expenditure would be justified for resurfacing if no maintenance is required for the first 5 years, $2000 per year for the next 10 years, $3000 per year for the next 5 years and $5000 a year thereafter? Assume the cost of money is 6%.
Problem 5 Mr. Jones wishes to establish a fund for his newborn childs education. The fund pays $60,000, $67,000, $75,000 and $83,000 on the childs 18th, 19th, 20th, and 21st birthdays respectively. The fund will be set up by the deposit of a fixed sum on the childs 1st through 17th birthdays. The fund earns 6 percent annual interest. What is the required annual deposit?
Problem 6 A company is pursuing following cost-reduction projects at the same time. 1. Project A requires an investment of $10 million. It is expected to yield a cost savings of $30 million in the first year and another $10 million in the second year. 2. Project B requires an investment of $5 million. It is expected to produce a cost savings of $5 million in the first year and another $20 million in the second year. 3. Project C needs an investment of $5 million. It is expected to produce a cost savings of $5 million in the first year and another $15 million in the second year. After the second year, there will be no benefit from these projects. The cost of capital is 10 percent. Determine the ranking of these projects on the basis of the evaluation criteria of NPV, IRR and Benefit-cost ratio.
Problem 7 a) An electric utility plans to build a large hydro project, to begin operation at the start of 2020. The ultimate project capacity will be 400 MW, but only 200 MW is required to serve load growth from 2020 until the end of 2024, and then the last 200 MW will be commissioned at the start of 2025. The foundations for the last 2100-MW units will be constructed initially, but the power house would be completed and the turbine-generator units would be installed later at an additional cost of $60 million. An alternative would be to include the last two units in the initial construction contract at an additional cost of only $45 million. The equipment suppliers and contractors could offer a lower price if all units were built in one stage due to economies of scale and thereby avoiding the cost of remobilisation required if the last units were built separately. Furthermore there is an opportunity to export the surplus generation produced by these last two units at an annual revenue of $ 4 million/yr, received at the end of each year from 2020 to 2024. Assume that the additional operation and maintenance costs of these last two units are $500,000/yr payable at the end of each year, the inflation rate is zero, the equipment lifetime is indefinite and the discount rate is 12%. Is it more economic to commission the last two units in 2020 or in 2025? b) Re-evaluate the alternative schemes described in the above problem with a discount rate of 15% instead of 12%. Which scheme is more economic now?
Problem 8 You are considering a good-looking Toyota hybrid car priced $60,000 or an elegant luxury BMW car at $50,000. The fuel efficiency is rated at 20 km/liter for the Toyota and 10 km/liter for the BMW. The annual maintenance cost for both cars is about 0.5% of the car price. The fuel price in the local market is selling at $1.00 per liter. The cars are to be driven about 20,000 kms per year. You plan to keep your car for five years only. At the fifth year, the resale values of the Toyota and the BMW are about 40 percent and 30 percent respectively, of their original prices. i) Assuming a discount rate of 5% and no escalation of fuel prices which car is the better choice from the standpoint of cost? ii) Will your decision change if the discount rate is 10%?
Problem 9 Determine the cost of electricity in US cents/kWh for a coal-fired power station of total capacity 500 MW, with the following cost and energy data: - Initial annual 5-years capital outlay 100, 200, 200, 100 and 100 MUS$ - Discount rate 8% - 25 years lifetime, assume salvage value of 50 MUS$. - Annual O&M cost: 1% of the total outlay (i.e. 1% of 700 MUS$) - Annual consumption of coal is 1 million tons - 1 ton of coal costs US$ 50.00 and produce 2500 kWh of energy - No inflation and real escalation of fuel Assume that all the costs and the benefit occur at the end of each year. Note that after the final disbursement of capital cost the power plant is brought on-line hence the benefit, O&M and fuel costs are realized after one year of plant being in operation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started