Problem 1: You can ignore the Effort (person-days) column. Just use the duration (days) column values for this problem. Task TI T2 T3 T4
Problem 1: You can ignore the Effort (person-days) column. Just use the duration (days) column values for this problem. Task TI T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12 Task T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 Homework. Develop Gantt Charts for the following 2 problems. T11 T12 T13 T14 T15 T16 Effort (person-days) 15 8 20 5 5 10 25 75 10 20 10 20 Problem 2: There are no milestones for this problem. Just use duration and dependencies. Duration (days) 10 15 10 20 10 15 20 35 15 5 10 20 35 10 Duration (days) 20 10 10 15 15 10 10 5 20 25 15 15 10 10 Dependencies TI (MI) T4 (M2) T3, T6 (M5) T7, T8 (M6) T9 (M7) T10, T11 (MB) T1 T2, T4 (M3) T1, T2 (M4) Dependencies T1, T2 TI (MI) T3, T4 T3 T7 T6 T10 T5, T9 T9 T3, T4 T8, T9 T2, T14 T15
Step by Step Solution
★★★★★
3.46 Rating (153 Votes )
There are 3 Steps involved in it
Step: 1
Here are the Gantt Charts for both problems Problem 1 Task Start Day End Day T1 0 20 T2 0 10 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started