Question

1 Approved Answer

Problem 2: Given the information: Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. Replace the

Problem 2: Given the information:

Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. Replace the "?" with your values. (15 points)

Place a "Y" in the last column, if the activity is critical.

Place an "N" in the last column, if the activity is non-critical.

Part 2:

Part 3: Given the information for this project, which activity do you think poses the most risk when it comes to having this project completed by its expected completion time? Explain your answer. And, if you are pointing out more than one activity, start the list with the riskiest, and then go down your list and explain your answer for each activity you chose to include. (5 points)

image text in transcribed Problem 2: Given the information: Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. Replace the "?" with your values. (15 points) Place a " Y " in the last column, if the activity is critical. Place an " N " in the last column, if the activity is non-critical. \begin{tabular}{|c|c|c|c|c|c|c|c|c|} \hline Activity & \begin{tabular}{c} Predecess \\ or \end{tabular} & \begin{tabular}{c} Optimist \\ ic \end{tabular} & \begin{tabular}{c} Most \\ Likely \end{tabular} & \begin{tabular}{c} Pessimist \\ ic \end{tabular} & te & & 2 & Critical (Y/N)? \\ \hline A & - & 4 & 13 & 25 & 13.5 & 3.5 & 12.25 & Y \\ \hline B & A & 3 & 12 & 21 & 12 & 3 & 9 & Y \\ \hline C & B & 8 & 11 & 14 & 11 & 1 & 1 & y \\ \hline D & B & 8 & 8 & 8 & 8 & 0 & 0 & Y \\ \hline E & B & 8 & 14 & 20 & 14 & 2 & 4 & y \\ \hline F & C, D & 14 & 20 & 26 & 20 & 2 & 4 & y \\ \hline G & D & 8 & 14 & 20 & 14 & 2 & 4 & n \\ \hline H & E, G & 4 & 7 & 10 & 7 & 1 & 1 & n \\ \hline \end{tabular} Part 2: Answer the questions below and replace the "?" with your values. (Show how the numbers are derived.) (20 points) 2.1. Expected completion of this project is? 2. Standard deviation of ciritical path is? 2.3. Probability of finishing this project 7 days sooner is? 2.4. Number of days needed to complete this project with an 80% probablity of being met Part 3: Given the information for this project, which activity do you think poses the most risk when it comes to having this project completed by its expected completion time? Explain your answer. And, if you are pointing out more than one activity, start the list with the riskiest, and then go down your list and explain your answer for each activity you chose to include. ( 5 points) Problem 2: Given the information: Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. Replace the "?" with your values. (15 points) Place a " Y " in the last column, if the activity is critical. Place an " N " in the last column, if the activity is non-critical. \begin{tabular}{|c|c|c|c|c|c|c|c|c|} \hline Activity & \begin{tabular}{c} Predecess \\ or \end{tabular} & \begin{tabular}{c} Optimist \\ ic \end{tabular} & \begin{tabular}{c} Most \\ Likely \end{tabular} & \begin{tabular}{c} Pessimist \\ ic \end{tabular} & te & & 2 & Critical (Y/N)? \\ \hline A & - & 4 & 13 & 25 & 13.5 & 3.5 & 12.25 & Y \\ \hline B & A & 3 & 12 & 21 & 12 & 3 & 9 & Y \\ \hline C & B & 8 & 11 & 14 & 11 & 1 & 1 & y \\ \hline D & B & 8 & 8 & 8 & 8 & 0 & 0 & Y \\ \hline E & B & 8 & 14 & 20 & 14 & 2 & 4 & y \\ \hline F & C, D & 14 & 20 & 26 & 20 & 2 & 4 & y \\ \hline G & D & 8 & 14 & 20 & 14 & 2 & 4 & n \\ \hline H & E, G & 4 & 7 & 10 & 7 & 1 & 1 & n \\ \hline \end{tabular} Part 2: Answer the questions below and replace the "?" with your values. (Show how the numbers are derived.) (20 points) 2.1. Expected completion of this project is? 2. Standard deviation of ciritical path is? 2.3. Probability of finishing this project 7 days sooner is? 2.4. Number of days needed to complete this project with an 80% probablity of being met Part 3: Given the information for this project, which activity do you think poses the most risk when it comes to having this project completed by its expected completion time? Explain your answer. And, if you are pointing out more than one activity, start the list with the riskiest, and then go down your list and explain your answer for each activity you chose to include. ( 5 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions

Question

4. Describe the role of narratives in constructing history.

Answered: 1 week ago

Question

1. Identify six different types of history.

Answered: 1 week ago