Problem 3 : An Assembly Line Balancing Problem A Shop works a 4 0 0 - minute day. The manager of the shop wants an
Problem : An Assembly Line Balancing Problem
A Shop works a minute day. The manager of the shop wants an output of units per day for the assembly line that has the elemental tasks shown in the table.
Task. Immediate successor. Tasktime.
a b c d
b e
c e
d f
e g j
f i
g h
h k
i j
j k
k m
m end.
Please:
Construct the precedence diagram.
Assign tasks using the mostfollowingtasks rule as the primary rule and the greatestpositionalweight rule as the secondary rule.
Compute the balance delay and the efficiency of your balance.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started