( Process Improvement ) There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out

(Process Improvement) There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this order. The processing time of each activity is given below:
\table[[Activity,Processing time (minutes per toy)],[Cutting,10],[Sewing,10],[Stuffing,5],[Assembling,5],[Packaging,25]]
Demand rate is 4 toys per hour. Currently we have worker A in charge of cutting, worker B in charge of sewing and stuffing, and worker C in chargr. of assembling and packaging.
a. If each worker is paid $10 per hour, what is the cost of direct labor associated with making one toy?
b. What is the labor content (in minutes) associated with making one toy?
c. What is the total idle time (in minutes)?
d. What is the average labor utilization?
e. What is the takt time (in minutes)?
f. What is the target manpower for the given demand rate?
g. If we balance the line by moving assembling to worker B, what is the average labor utilization?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions