Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Process quality control is measured by sampling 10 items each day over a seven-day period. The overall mean of the items sampled is 9.3 with

Process quality control is measured by sampling 10 items each day over a seven-day period. The overall mean of the items sampled is 9.3" with a standard deviation of 2.1." What is the standard error of the process?

Assuming a Z-score of 1.96, what are the upper and lower control limits for the process?

The goal is for the item to be 9" with an acceptable tolerance of 0.5." What are Cp and Cpk?

A new manufacturing method is introduced. It takes 200 seconds to make the first item and they expect to be on an 80% learning curve. How long will it take to make the 25th item?

A second new method is introduced. It takes only 180 seconds to make the first item and 30 seconds for the 150thitem. What is b in their learning curve formula?

A third new method takes 220 seconds for the first item and 120 seconds for the 400th item. What is the rate of learning?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions

Question

Where do I fit in?

Answered: 1 week ago