Processing times ( including setup times ) and due dates for six jobs waiting to be processed at a work center are given in the
Processing times including setup times and
due dates for six jobs waiting to be processed at a
work center are given in the following table.
Determine the sequence of jobs, the average
flow time, average tardiness, and average number
of jobs at the work center, for each of these rules:
FCFS SPT EDD, CR