Project A and B both have positive NPVs. If A and B are mutually exclusive, others thing held constant, which project will management accept? Multiple
Project A and B both have positive NPVs. If A and B are mutually exclusive, others thing held constant, which project will management accept?
Multiple Choice
-
Management will accept both A and B since they both have positive NPVs.
-
When projects are mutually exclusive, the NPV rule is ignored and neither project is accepted.
-
Management will accept the project with the lower NPV.
-
Management will accept the project with the higher NPV.