Question

1 Approved Answer

Project details: Approved budgeted cost of the warehouse walls are $150 per linear meter. Warehouse has four equal sides of 200 meters each. according to

Project details:

  • Approved budgeted cost of the warehouse walls are $150 per linear meter.
  • Warehouse has four equal sides of 200 meters each.
  • according to the approved schedule, wall completion is planned to be 100 linear meters per day.
  • Culvert installation is budgeted to cost $7500
  • Planned completion of the project is 8.5 days

At the end of Day 3:

  • Culvert was installed prior to the first wall.
  • The first wall is fully installed.
  • The second wall has 50 meters of wall erected.
  • $40,000 has been spent in total.
  • EV = 7500 + (250)(150) = $45,000
  • AC = $40,000
  • PV = 100(2.5)(150) + 7500 = $45,000

As the Project Manager (PM), calculate:

  1. What is CPI (Cost Performance Index)?
  2. What is SPI (Schedule Performance Index)?
  3. What is BAC (Budget at Completion)?
  4. What is EAC (Estimate at Completion)?
  5. What are the variances (SV, CV, VAC)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management Building Measuring and Managing Brand Equity

Authors: Kevin Lane Keller

4th edition

9780273779414, 132664259, 273779419, 978-0132664257

More Books

Students also viewed these General Management questions

Question

What is the main advantage of gemfibrozil over bezafibrate?

Answered: 1 week ago