Project details: Approved budgeted cost of the warehouse walls are $150 per linear meter. Warehouse has four equal sides of 200 meters each. according to
Project details:
- Approved budgeted cost of the warehouse walls are $150 per linear meter.
- Warehouse has four equal sides of 200 meters each.
- according to the approved schedule, wall completion is planned to be 100 linear meters per day.
- Culvert installation is budgeted to cost $7500
- Planned completion of the project is 8.5 days
At the end of Day 3:
- Culvert was installed prior to the first wall.
- The first wall is fully installed.
- The second wall has 50 meters of wall erected.
- $40,000 has been spent in total.
- EV = 7500 + (250)(150) = $45,000
- AC = $40,000
- PV = 100(2.5)(150) + 7500 = $45,000
As the Project Manager (PM), calculate:
- What is CPI (Cost Performance Index)?
- What is SPI (Schedule Performance Index)?
- What is BAC (Budget at Completion)?
- What is EAC (Estimate at Completion)?
- What are the variances (SV, CV, VAC)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started