Project estimate information is provided as follows: Optimistic cost = $900 Most likely cost =$1000 Pessimistic cost = $2100 Use the Rule of 6, PERT
Project estimate information is provided as follows:
- Optimistic cost = $900
- Most likely cost =$1000
- Pessimistic cost = $2100
Use the Rule of 6, PERT to calculate the best estimate based on the above information
$1000
$1333
$1167
$2333