PV System System size to install= 1 MWp System life = 30 years Cost = 1 JD/Wp Utilization Factor = 21% Dust cleaning cost =
PV System
System size to install= 1 MWp System life = 30 years Cost = 1 JD/Wp Utilization Factor = 21% Dust cleaning cost = 250 JD/month
Calculate LCOE?
Wind System1.5 MW turbine UF = 50%Cost of turbine = 1000 JD/kWO&M cost = 20 JD/kW/year System life = 25 years
Calculate LCOE?
HW: Solve both questions for PV and wind systems with the assumption of 10% discount rate