Q . 1 1 A small marketing project consists of number of activities. Normal time ( in days ) , a minimum or crash time
Q A small marketing project consists of number of activities. Normal time in days a minimum or
crash time in days and the cost in Rs per day of crashing each activity is as follows:
You are required to
a Find out the normal project length and the minimum project length.
b Determine the minimum crashing cost of schedules ranging from normal length down to and
including the minimum length schedule, ie if is the length of the normal schedule, find the cost of
schedules which are and so on days long. If overhead cost total is Rs per day, what
is the optimal length schedule duration on each activity for optimal solution
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started