Question

1 Approved Answer

Q) Which of the following is NOT a characteristic of a project life cycle? A. The project life cycle determines which transitional actions at the

Q) Which of the following is NOT a characteristic of a project life cycle?

A. The project life cycle determines which transitional actions at the beginning and end of the project are included, so that the project can be linked to the ongoing operations of the performing organization.

B. Ability of the stakeholders to influence final characteristics of the project's product increases as the project progresses

C. Stakeholder influence, risk, and uncertainty are highest at the start of the project.

D. Stakeholder influence, risk, and uncertainty decrease as the project progresses.

q2) A stakeholder has a bad reputation of requesting many changes. How will you manage this stakeholder?

A. Ignore him.

B. Involve him from the beginning of the project

C. Flatly deny all of his requests.

D. Speak with management

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

11th edition

978-0133872460, 133872467, 133872130, 978-0133872682, 133872688, 978-0133872132

More Books

Students also viewed these General Management questions