Q1 - Provide a Work Breakdown Structure (WBS) for the following scope: Requirement 1: 3 bedrooms Requirement 2: 2.5 bathrooms Requirement 3: Pool Requirement 4:
Q1 - Provide a Work Breakdown Structure (WBS) for the following scope:
- Requirement 1: 3 bedrooms
- Requirement 2: 2.5 bathrooms
- Requirement 3: Pool
- Requirement 4: 2 patios, one patio should be enclosed
Q2
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
Activity | Predecessor | Duration in Days |
A | Start | 3 |
B | Start | 6 |
c | A, B | 12 |
D | B | 5 |
E | D | 4 |
F | C | 6 |
G | E,F | 8 |
H | E | 7 |
I | H | 3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started