Q1 The following particulars find out labour variance. Std hour =250 hour Std rate for actual production = 1.5 OMR per hour Actual hour =200
Q1 The following particulars find out labour variance.
Std hour =250 hour
Std rate for actual production = 1.5 OMR per hour
Actual hour =200 hour
Actual rate=1.6 OMR per hour
Q 2 Calculate the Material Cost Variance from the following information:
Standard Price of material per kg = OMR 3.8
Standard Usage of materials = 750 kgs
Actual Usage of materials = 900 kgs
Actual Price of materials per kg = OMR 2.9