Q2. Given the estimated activity times below and the network in problem Ql above: Activity 3 m b A 6.5 7.5 14.5 B 8.5

image text in transcribed
Q2. Given the estimated activity times below and the network in problem \"Ql \" above: Activity 3 m b A 6.5 7.5 14.5 B 8.5 10.5 12.5 C 2.5 3.5 4.5 D 6.5 7.5 8.5 E 5.5 5.5 9.5 F 5.5 7.5 9.5 G 4.5 6.5 8.5 H 2.5 3.5 3.5 What is the probability that the project will be completed within (based on the path with the longest expected time): a. 21 days? b. 22 days? c. 25 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions