Q2. Given the estimated activity times below and the network in problem Ql above: Activity 3 m b A 6.5 7.5 14.5 B 8.5
Q2. Given the estimated activity times below and the network in problem \"Ql \" above: Activity 3 m b A 6.5 7.5 14.5 B 8.5 10.5 12.5 C 2.5 3.5 4.5 D 6.5 7.5 8.5 E 5.5 5.5 9.5 F 5.5 7.5 9.5 G 4.5 6.5 8.5 H 2.5 3.5 3.5 What is the probability that the project will be completed within (based on the path with the longest expected time): a. 21 days? b. 22 days? c. 25 days