Q4. LOGIC: On the start of the project 2 activities A&B start in parallel, on the finish of activity B activity D can start ,&

image text in transcribed

Q4. LOGIC: On the start of the project 2 activities A&B start in parallel, on the finish of activity B activity D can start ,& on the finish of both the activities A&B activity C can start. When activity C finishes activity E can start & when both the activities i:e C&D finish activity F can start. On the finish of activity F, activities G, H & I start in parallel. When activity G finishes activity J starts . Activities J, H &I give output to activity K. Activity K & E give output to activity L which is the last activity of the project, Task A Optimistic 5 Pessimistic Most Likely 8 B 18 22 20 D 16 20 18 26 40 33 E 15 25 20 F 6 12 9 G 7 12 10 H 3 5 4 I 10 18 15 J 2 6 4. K 20 25 22 10 L 10 15 12 From the given logic and the data do the following:- (i) For each task determine the expected task time and their variance. (ii) Draw the network diagram in AIB format. Determine ES and EF of each activity. (iv) Find the critical path of the project. (20)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Practical Database Programming With Visual Basic.NET

Authors: Ying Bai

1st Edition

0521712351, 978-0521712354

More Books

Students also viewed these Databases questions