Question: Q4 v2 (50 marks) Materlal Requlrements Planning Using the master schedule of Figure 25.2(b), and the product structures in Figures 25.4 and 25.6, determine the

Q4 v2 (50 marks) Materlal Requlrements Planning Using the master schedule of Figure 25.2(b), and the product structures in Figures 25.4 and 25.6, determine the time-phased requirements for component C6 and raw material M 6 , and provide a short narrative explaining your working/steps (up to 250 words). Lead times are as follows: for P1, assembly lead time is 1 week; for P2, assembly lead time is 1 week; for 52 , assembly lead time is 1 week; for 53 , assembly lead time is 1 week; for C6, manufacturing lead time is 2 weeks; and for M6, ordering lead time is 2 weeks. The current inventory on hand and on order for 53, C6, and M6 is as follows: for 53, inventory on hand is 2 units and quantity on order is zero; for C6, inventory on hand is 5 units and quantity on order is 10 for delivery in week 2 ; and for M6, inventory on hand is 10 units and quantity on order is 50 for delivery in week 2 . The format of the solution should be similar to that presented in Figure 25.7. (50 marks; 20 marks given for correct outline of plan (table); 20 marks for correct materials requirement; 10 marks for narrative explaining your working/steps) Q4 v2 (50 marks) Materlal Requlrements Planning Using the master schedule of Figure 25.2(b), and the product structures in Figures 25.4 and 25.6, determine the time-phased requirements for component C6 and raw material M 6 , and provide a short narrative explaining your working/steps (up to 250 words). Lead times are as follows: for P1, assembly lead time is 1 week; for P2, assembly lead time is 1 week; for 52 , assembly lead time is 1 week; for 53 , assembly lead time is 1 week; for C6, manufacturing lead time is 2 weeks; and for M6, ordering lead time is 2 weeks. The current inventory on hand and on order for 53, C6, and M6 is as follows: for 53, inventory on hand is 2 units and quantity on order is zero; for C6, inventory on hand is 5 units and quantity on order is 10 for delivery in week 2 ; and for M6, inventory on hand is 10 units and quantity on order is 50 for delivery in week 2 . The format of the solution should be similar to that presented in Figure 25.7. (50 marks; 20 marks given for correct outline of plan (table); 20 marks for correct materials requirement; 10 marks for narrative explaining your working/steps)